Friday, 27 November 2026
Economy

500 kV Khalkha Substation Worth $171.4 Million Launched in Tashkent Region

On November 7, voltage was supplied to the 500 kV Khalkha substation with a capacity of 1602 MVA in the Tashkent region. The $171.4 million project was implemented with the participation of the World Bank.

09 Nov, 13:33Read in Russian
gov.uz

On November 7, voltage was supplied to the new Khalkha substation in the Tashkent region of Uzbekistan, the Ministry of Energy reported. The facility, with a capacity of 1602 MVA, has become one of the largest and most modern elements of the country's high-voltage infrastructure.

The substation is expected to enhance the reliability of electricity supply for Tashkent and part of the Tashkent region, as well as help distribute the load more evenly across existing networks. As part of the project, high-voltage overhead power transmission lines were constructed: 213 kilometers of 220 kV lines and 72 kilometers of 500 kV lines.

The ministry anticipates that redistributing the load will reduce the burden on the Tashkent Thermal Power Plant. This will allow for the discontinuation of fuel oil use and contribute to improving the environmental situation in the capital and surrounding areas by reducing pollutant emissions.

The project was implemented with the participation of the World Bank. Currently, final work is underway to fully integrate the substation and lines into Uzbekistan's unified power system.

The Ministry of Energy believes that the created infrastructure will expand electricity transmission capabilities, improve the distribution of its flows, and help more reliably meet growing demand.